Tuesday, December 6

Ninth week

From Peng
To file
12/6/2011
Test12
12-8x9-ledger-OSB-54mil-8’up seam cyclic
Pretest
43circles
Reference displacement:2.92x0.6in.
8’x9’ shear wall, horizontal seam at 8’up.Vertical seam at 4’over.
Strap is good.
2 over-drilling screws at the horizontal seam recorded
Anchor spacing is 2’

After test
Peak load+:10049lbs
Displacement: 2.2672in.
Peak load-:-8443.1lbs
Displacement:  -1.6616in.
The failure occur at the bottom, fastener pull through OSB with titled
Fasteners up to 2’high on the chord studs pull through the OSB
At the bottom vertical seam which is up to 1’, the fasteners fail with wood bearing failure and pulling through OSB.
The strap is good, no damage observed
The outside of the horizontal seam tear out.
The connection of the vertical and horizontal seam is broke because of the contact.
Fasteners in the corner at the bottom are cut off the head.
Photo

 After test
Bottom fasteners (1)
 Bottom fasteners (2)
 Bottom fasteners (3)
 Bottom fasteners (4)
 Bottom 